Transmission bottlenecks are holding up wind and solar projects » Yale Climate Connections


Transcript:

Solar and wind farms can help the U.S. meet its rapidly growing demand for electricity. And there are lots of new clean energy projects ready to break ground.

But the country’s transmission infrastructure poses a bottleneck. And energy developers often spend years waiting for approval to connect a project to the grid.

Gramlich: “The big transmission lines that you see when you drive along the highway are what a lot of the large wind, solar, and battery storage developers are trying to connect to, and they connect specifically to substations.”

That’s Rob Gramlich of the consulting firm Grid Strategies. He says before utilities and grid operators greenlight a project, they have to assess whether the grid can handle the added electricity in that location or whether it will require upgrades.

It’s a slow, expensive process with a long backlog. But if passed, a new federal bill would require regulators to shorten it.

And government agencies and grid operators are working to streamline the process – for example, by studying clusters of projects at once, or prioritizing projects in areas with lots of transmission capacity to get them online more quickly.

It’s a complicated challenge, but Gramlich is optimistic.

Gramlich: “The regulations are difficult, the politics are difficult, but we can overcome those things.”

Reporting credit: Sarah Kennedy / ChavoBart Digital Media





Source link

Zosia Mamet Says ‘Horrible’ Boss Made Her Quit Classic Show

Russia launches Progress cargo ship to the International Space Station

Leave a Reply

Your email address will not be published. Required fields are marked *